Designing for success: how we’re enabling 714MW of offshore wind energy
East Anglia One
East Anglia One is a large offshore wind farm under construction by Scottish Power Renewables to form part of the wider East Anglia Array. Once complete, up to 102 wind turbines with a 7MW generation capacity will power homes for years to come.
We have delivered a range of services for the EA One scheme since 2012. Our experienced teams have been embedded within the client team to ensure high value outcomes and low risks for the project, from procurement through to operations and maintenance, and we continue to play a key part in the development of the project.
Using data to avoid programme risks
Our involvement with Scottish Power Renewables began in 2012 when we undertook a foundation concept role. We then undertook ecology and mitigation studies for the construction of 37km of onshore cabling, whilst taking into consideration how seasonality could cause potential programme delays. We used GIS data-capture technology, remote image recording and a range of ecological field surveys to help progress the project to the next stage.
Developing a resilient programme
The offshore construction and installation for EA One is underway and will be completed by 2020 - ensuring that the programme is set up for success was a crucial element for Scottish Power Renewables. Since 2015 we’ve worked to reduce the procurement risk associated with the £2.6bn offshore installation and used this as an opportunity to identify cost savings.
Our risk engineering experts worked with various contractors including substation and cabling contractors to obtain frequent updates, ensuring all possible risks were recorded with a contingency value assigned to it whilst mitigating wider project risks. Our role in managing and avoiding risk supported senior leaders in their decision making for next project steps.
Understanding the technical requirements and adding value
Our experienced maritime and ports team successfully integrated with the client team on site, this has enabled collaboration and efficient ways of working. As one collaborative team, we have overseen the assessment, procurement and specification of upgrade works for construction management, operations and maintenance, foundations marshalling and wind turbine assembly facilities.
We conducted in-depth reviews of the supply chain logistics for each facility, along with technical reviews of the existing infrastructure and scoping and costing of new infrastructure. This allowed us to establish significant areas to avoid project risks and minimise cost – we helped to reduce risk associated with £40m+ of ports contracts, and more critically the impact on the wider project.
Our team of maritime experts assessed ports across the UK, Belgium and the Netherlands for their technical and commercial abilities, before final negotiations and agreements with the Ports of Lowestoft, Great Yarmouth and Vlissingen were reached.
Being an integral part of the client team allowed us to determine the technical requirements for a foundation marshalling port. Following a specific approach to the selection, our team worked with the chosen port contractor to refine the layout plan as well as the load-in/load-out processes. This enables the accommodation of:
- 36 800 tonne jacket foundations standing 65m tall
- 100 piles weighing up to 144 tonnes, ranging in length from 39-55 metres
A one-stop-shop for concept design
The operation and maintenance of a wind farm is key to ensuring secure and resilient energy. We established the reference design for a three-storey mixed use office and warehouse including a marine coordination centre, offshore personnel terminal and a critical spares warehouse – essential to the day-to-day running of the whole development.
As part of our procurement role, we identified potential risks and navigated the client through any construction tender issues. We worked to optimise requirements and keep estimated construction costs within the available budget.
Supporting essential day-to-day operations and maintenance
The new operations and maintenance building will support the daily operations of the windfarm. The base, completed in October 2019, is conveniently situated quayside for easy access to crew transfer vessels that transport maintenance teams to the wind farm in the North Sea. Around 100 people will be employed full-time at the base when East Anglia One is completed, and the thousands of contractors and supply chain operators using the site every year will contribute substantially to the local economy.
Design innovation across a large programme portfolio
With many components involved in the EA One development, we further supported the client using our detailed design skills. We undertook a feasibility study to assess innovative materials that could be used to construct an offshore wind demonstration platform on behalf of Scottish Power Renewables.
The starting of construction on our new operations and maintenance building in Lowestoft is a landmark moment for the East Anglia One project and shows our commitment to the local area. The new operations and maintenance facility, will be a hive of activity for engineers and technicians, the base for marine operations, specialist offices and warehousing. It will also help to support the offshore phase of construction work on the windfarm, as well as the 30-plus years operational lifespan of the project.
Charlie Jordan
Scottish Power Renewables Project Director for East Anglia One
Delivering across the wider East Anglia Array
With the development forming the first part of the wider East Anglia Array development - totalling four sites in close proximity, all at different phases - Arup specialists from across the UK have been involved to ensure wider project success.
We continue to work with Scottish Power Renewables including developing succinct contractor employer’s requirements for the EA Three OFTO network transmission assets. Our offshore design specialists have also been carrying out feasibility studies for suction bucket technology to be used as a potential foundation option for the next project phase.
What we delivered
-
Evaluating and progressing key programme deliverables for the East Anglia Array wind farm
-
Defining and delivering the most efficient way to build and maintain the 102-turbine windfarm in the North Sea
-
Using advanced digital design to assess the feasibility of innovative materials and build techniques for Scottish Power Renewables
Get in touch with our team
Projects
Explore more energy projects
Early-stage advice on the foundation design for a Scotland offshore substation
Stoura Offshore Wind Farm, UK
Supporting the successful delivery of Denmark’s largest offshore wind farm
Project Thor, Denmark
Developing a sustainable biomethane fuel production plant in Spain
Biomethane Initiatives JV – Noez Plant, Spain
First hillside solar plant in the Philippines
Cayanga Hillside Solar Farm, Philippines
Get in touch with us
If you'd like to speak to one of our energy experts about any of the issues raised on this page or a potential collaboration then please get in touch by completing the form.