MBTA Green Line Extension, Boston, MA

A major MBTA design-build project linking Downtown Boston with Union Square and College Ave

The Green Line Extension (GLX) provides the first direct rail link connecting Downtown Boston to Union Square in Somerville and College Avenue in Medford, two densely populated, historically underserved areas. Slated for completion in late 2021, this major Massachusetts Bay Transportation Authority (MBTA) design-build project is forecast to add 50,000 daily passenger trips to Boston’s transit network. The GLX will put the city one step closer to meeting its goal of carbon neutrality by 2050 by significantly reducing vehicle trips and associated air emissions. The project includes the construction of just over four miles of new rail tracks, the relocation of existing tracks and one station, and the addition of six new stations, as well as a variety of infrastructure upgrades.

The GLX has been on the drawing board since 1990 but didn’t break ground until 2012. Three years into the design process, in August 2015, the MBTA disclosed that the project’s costs had ballooned to $3bn—an increase of more than $1bn over previous estimates.

Arup’s initial involvement in the project began in October 2015 when we were hired to perform a full-scale evaluation of all aspects of the project—from scope and schedule to programming and procurement. The assessment identified a variety of interventions that could be used to bring the project’s cost back within original projections.

The MBTA cancelled the project in December 2015 and formed a multidisciplinary Interim Project Management Team (IPMT) to undertake a preliminary redesign aimed at:

  • Reducing the project’s cost while maintaining core functionality and benefits

  • Exploring alternative procurement options

  • Developing a realistic cost estimate and schedule

  • Ensuring that the revised project still met the necessary requirements to attain federal funding.

As a key member of IPMT, we provided critical technical re-engineering, estimating and scheduling that aided the client in cutting the cost of the project by roughly $700 million.

Project Summary


4 miles of new tracks

6new stations

$700mreduction in project costs

Lowering costs and increasing efficiency  

Over the first three years of the GLX project, the original project team worked hard to fulfill the needs and desires of a broad base of public and community stakeholders — many with grand aspirations for the long-awaited transit line. The outcome of these efforts was an inflated project scope and a steep increase in costs. When Arup came on board in October of 2015, it was our job to determine if the project could be scaled back to something more efficient and affordable, while still performing at expected levels.

Delivered in just six weeks, our assessment report provided a list of recommendations that shaved a full 19 months off the schedule and reduced the project’s cost by $700m. These recommendations included: downsizing stations to eliminate redundancies and unnecessary flourishes; rehabbing some of the bridges inside the project’s footprint instead of replacing them; and—most significantly—delivering the project with design-build instead of a construction manager/general contractor delivery model. Our recommendations were included in the IPMT’s full list of recommendations and played a critical role in bringing the revised estimated cost of the program down to $2.3bn.

A trusted design-build partner

“The decision to go design-build cut close to a year and a half off the overall project schedule—that's a year and a half of contractors' costs,” says Jeff Tubbs, Arup’s Design Professional Project Director. “GLX is the biggest design-build project the MBTA has taken on and Arup’s experience with successfully delivering design-build projects helped give them the confidence to move forward.”

After the decision was made to pursue design-build, the MBTA hired us to assist in the preparation of a set of design-build documents that reflected the descoped design. Eventually, we took on full responsibility for the preparation of these documents. The firm's previous experience with the design-build process proved so valuable to the MBTA that we were then appointed to serve as Design Professional, a role that involved helping the client define internal design-build procurement protocols and assisting them in authoring the Technical Addenda for a request for proposals to select a constructor to ensure that the project achieved the necessary performance standards. We also reviewed the new scope to validate that it met the necessary criteria to continue qualifying for 50% federal funding, performed cost estimating, and reviewed all submitted technical proposals.

In November 2017, GLX Constructors was chosen to construct the project, and we were selected to continue in the role of Design Professional to assist the MBTA throughout the project’s design and construction phases. 

A perfect deadline track record

Given the project’s previous issues and postponements, MBTA Program Manager John Dalton was committed to seeing the redesign and procurement proceed according to a strict schedule. In our role as Design Professional, we have successfully met all deadlines. This has involved the review of over 180 design package submittals; the review of Management Plans; and submitting responses to over 200 Requests for Information (RFIs) to date–all of which has been completed on time and within budget. This level of efficiency was achieved by embedding a team of eight Arup staff and subconsultants with the client and drawing on more than 100 engineers and consultants at various Arup offices. 

On the path to completion 

Construction of the GLX broke ground in early 2019, with initial efforts focused on widening two existing railroad right-of-ways to make room for the addition of over 4-miles of new track, a massive undertaking involving the relocation of tons of dirt and the coordinated efforts of 390+ people, according to the Boston Globe.

The much-anticipated project is reported to be on schedule for a late 2021 opening.