Sibanye Gold planned to invest in a 200MW ground-mounted PV facility at the company’s project base in South Africa. The PV facility was being developed to offset the company’s energy demand from the grid, resulting in lower operational costs
Arup undertook the concept design and basic design based on the 1500V technology, which enabled the use of fewer inverters, fewer string monitor boxes and shorter return DC cables, reducing costs. We used more PV modules per inverter, reducing the number of access roads needed.
We also provided technical support for the environmental authorisations and permits required.Thanks to this facility, Sibanye Gold was able to offset its energy demand from the grid, resulting in lower operational costs.On completion, the PV facility was one of the largest of its kind in the Southern Hemisphere.
Providing crucial technical input
We provided technical input into the developer bidding process and oversaw the technical evaluations of bid responses, which allowed us to reduce costs from the early stages of the project. Due diligence on tracker structures tilting and a cost analysis determined that the tracking of panels was not feasible, leading to a reduction in cost. Further analysis assessed a phased rate of construction in order to cut construction costs and minimise loss of energy disruptions.
What we delivered
Arup undertook the design for the tender package for a 200MW solar photovoltaic (PV) facility.
The work encompassed electrical and civil design as well as associated design specifications and bill of quantities.
We also provided technical support for the environmental authorisations and permits required.
If you'd like to speak to one of our energy experts about any of the issues raised on this page or a potential collaboration then please get in touch by completing the form.