Building a state-of-the-art new home for the Las Vegas Raiders - Allegiant Stadium
Allegiant Stadium
Allegiant Stadium is the Las Vegas Raiders football team’s new home on the iconic Las Vegas Strip. With 65,000 seats – that can be expanded by an additional 7,000 during major events – it is the largest entertainment venue in the city. The stadium is expected to generate $62 million of economic benefits annually while creating 6,000 jobs.
Arup, in partnership with architect of record HNTB, design architect Manica Architecture, project manager CAA Icon, and Mortensen & McCarthy Joint Venture (MMcJV), helped bring the unique stadium to life, providing structural and façade engineering as well as building maintenance for the project.
Enabling flexible spaces
The stadium will be used for a variety of events beyond football games and has been designed to be adaptable for all events, from professional and college football to concerts. It features walls that open to views of the Las Vegas Strip, as well as a translucent cable-truss supported roof.
Allegiant Stadium is one of two domed stadiums in the US with a retractable natural grass playing field, a must-have element for the Raiders organisation. Arup designed retractable columns and transfer trusses to allow the 220-foot-wide self-propelled field to roll underneath the four-story south stand and to the outside parking position, allowing grass to grow in unobstructed sunlight. When the field is returned to the indoor playing position, the columns are put back in place using hydraulic actuators to ensure occupant comfort and to meet vibration requirements.
Arup helped ensure significant steel savings by implementing a scenario-based design approach and a rigorous operations procedure, in which lower design loads could be safely ensured during field tray movement operations, when the columns are retracted.
Incorporating a cable truss roof
To achieve the architectural design, Arup incorporated a lightweight and delicate cable truss roof. Unusual in the United States, this structure normally requires more precise construction requirements and methods to achieve. Typically, the entire steel compression ring structure is built and test-fitted offsite to ensure the tight requirements for the cables are met, then disassembled and shipped to the project site. This adds cost and time to the construction schedule due to multiple iterations where the steel is assembled and disassembled as it is adjusted to fit.
To save time and money, Arup implemented a unique design using 54 field adjustable nodes. These nodes could be adjusted to the right tolerance at the interface to the cable structure – all without impacting the fabrication and erection of the steel canopy. Multiple surveys of the steel canopy at the end of fit-up and erection ensured that each node was properly adjusted to within 25mm of its required position prior to the cable big lift. Then the cables, which had been precisely cut to length months earlier in Switzerland and shipped to Las Vegas without any splices, were rolled out onto the field, lifted, and prestressed into position to support the transparent inflated ETFE (Ethylene Tetrafluoro-ethylene) pillow roof.
Delivering an ambitious project
From concept design to completion in only 40 months, Allegiant Stadium is the fastest designed and constructed US football stadium of its size. The fast-track Design-Build delivery method was essential in completing the stadium on budget and on time for the start of the 2020/21 football season. Working together with the Clark County Department of Building and Fire Prevention, Arup implemented a collaborative review and permitting approach to allow MMCJV to start work on the foundations and concrete bowl structure four months prior to permitting the steel and cable structure above.
At the same time, Arup issued an early steel mill order and detailing sequences to the steel fabricator to ensure the structural steel was ready to start erection the day the final structural permit was pulled. Arup created the structural steel design model in Tekla, the industry standard fabrication model software, to allow the project team to collaborate and share BIM content directly with the builder with no missed translations as designs moved between platforms. In addition, our digital team created automated tools to regularly convert the Tekla model into a native Revit model for cloud collaboration with the rest of the design team.
CAA ICON / Mortensen &McCarthy / Manica Architecture (Design Architect) / HNTB (Architect of Record) / Mortensen & McCarthy JV (MMcJV) / Las Vegas Stadium Event Company
What we delivered
-
Bringing the largest entertainment venue in Las Vegas to life by providing structural and façade engineering, as well as building maintenance, to the project.
-
Designing the stadium to be flexible and adaptable for multiple sporting and non-sporting events.
-
Leveraging Arup’s multidisciplinary skillset and innovative approach to design to contribute standout elements of the stadium’s unique roof and retractable field designs.
Get in touch with our team
Projects
Explore more sport projects
Realizing a sustainable, world-class athletic facility through innovative mass timber design and energy-efficient mechanical systems
San Antonio Spurs Victory Capital Performance Center, USA
Sustainable design for Italy's largest indoor venue
CTS Eventim Arena, Italy
Redesigning Madrid’s legendary Santiago Bernabéu football stadium to welcome an ever-growing audience
Santiago Bernabéu stadium, Spain
Alexander Stadium: Delivering a sporting and community legacy for Birmingham
Alexander Stadium, UK
Get in touch with us
If you'd like to speak to one of our sport experts about any of the issues raised on this page or a potential collaboration then please get in touch by completing the form.